Pole Attachments - Construction Standards
Allocation of Costs for Rearrangement, Relocation and Removal of Facilities
(a) The costs for any rearrangement, relocation and removal of Licensee's
facilities not requested by the Licensee, including those required by Articles
8, 9, 10 and 14 shall be allocated to the Licensor, Licensee or other entity
on the following basis:
(1) if the rearrangement, relocation or removal of Licensee's facilities is
the result of an additional attachment or the modification of an existing
attachment sought by and entity other than the Licensor or Licensee, Licensee
may request reimbursement for transfers or rearrangements from the third party
requesting the modification;
(2) if the rearrangement, relocation or removal of Licensee's facilities is
the result of the need to upgrade or reconfigure Licensor's energy
distribution/transmission system, the Licensee shall be responsible for the
rearrangement, relocation or removal of Licensee's facilities provided however
that Licensor shall make such transfers as may be applicable if Licensee has
elected to purchase services included in the bundled services rate as set
forth in Exhibit D. Licensor shall make a good faith effort to provide
Licensee with adequate notice of the need for the rearrangement, relocation or
removal and attempt to minimize the need for rearrangement, relocation or
removal of Licensee's facilities. If rearrangement, relocation or removal of
Licensee's facilities is required which Licensor would not make under the
bundled rate in Exhibit D, Licensee shall make such modifications as quickly
as possible.
(b) Where Licensor rearranges its facilities to accommodate Licensee, Licensee
shall pay Licensor's estimated cost of rearrangement in advance and Licensor
shall thereupon make such changes in accordance with Exhibit A. Said estimate
expires after the lapse of three (3) months.
(c) In the event a request for attachments is made by Licensee and steps are
taken by Licensor to carry out the request by performing necessary engineering
and administrative work and the job is canceled by Licensee causing the job
not to be done or completed, Licensee shall reimburse Licensor for the actual
costs incurred by Licensor with respect to the canceled job, including
engineering, clerical, administrative and construction costs.